The Engineering consultant contracted us to install and commission metocean instruments that will be used during the operation of the TEMA LNG Terminal facility. the installation was in the following phases:

  1. Construction of the concrete base
  2. Installation of concrete base and all equipment
  3. Installation of Cables on the BD02 to FRU.

The construction of the concrete base was done within a week in the month of August 2021 whiles the installation of the wave Sensor and cables were done in the month of December 2021. The timing of the works was coordinated by the Consulting Engineer.